3 years after construction started, MRT-7 almost 50% complete — DOTr

By: - Reporter /
/ 04:30 PM November 11, 2019

MANILA, Philippines — Three years after construction, the Metro Rail Transit Line 7 (MRT-7) is almost half to completion, the Department of Transportation (DOTr) said on Monday.

The construction for the 22.8-kilometer elevated train line which will run from North Avenue in Quezon City to San Jose del Monte City in Bulacan province started in August 2016.

Citing the latest project status report, DOTr said the MRT-7 is 49.22%.

Article continues after this advertisement

https://www.facebook.com/130406490431829/posts/1513897105416087?d=n&sfns=mo

FEATURED STORIES

Civil works on the guideway are in various stages of construction, while civil works of nine of the 14 train stations are in “full swing.”

Installation of tracks is also ongoing, the DOTr said. The required rolling stock of 108 cars have also been completed and is ready to be shipped pending on the availability of the holding area.

Article continues after this advertisement

The MRT-7 is eyed to be completed by 2022, the agency said. It aims to cut travel time between the two endpoints from two to three hours to 35 minutes. It is expected to carry about 28,000 passengers an hour per route or about 350,000 commuters a day.

Article continues after this advertisement

The P69.3-billion project, which was started under the administration of former President Benigno Aquino III, was initially eyed to be finished this year.

Article continues after this advertisement

READ: MRT 7 to Bulacan finally breaks ground

However, its completion was delayed due to right-of-way issues, the DOTr earlier explained.

Article continues after this advertisement

READ:

The project is backed by conglomerate San Miguel Corp. (SMC). The firm will also operate the MRT-7 under a 35-year concession agreement. It was the Hyundai Rotem-EEI group that was tapped to build the project.

The train line will have 14 stations including a station in the Quezon City Memorial Circle, University Avenue, Tandang Sora, Don Antonio, Batasan, Doña Carmen, Regalado, Mindanao Avenue, Quirino, Sacred Heart, and Tala.

At North Avenue, the MRT-7 will connect with the existing Light Rail Transit Line 1 and the Metro Rail Transit Line 3 through the Unified Common Station project.

RELATED STORIES:

Firm urged to explain delay in MRT 7 construction

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the and acknowledge that I have read the .

MRT 7 contractor fined P25K

MOST READ
www
business
www
globalnation
business
TAGS: Construction, DoTr, Metro, MRT-7

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the and acknowledge that I have read the .

© Copyright 1997-2024 | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies.