Marcos directs DOTr to renegotiate loan agreements for 3 railway projects

By: - Reporter /
/ 03:54 PM July 16, 2022

UPGRADES ON TRACK The refleeting program of the Philippine National Railways (PNR) gets a boost with the acquisition of three diesel hydraulic locomotives and 15 passenger coaches from Indonesian manufacturer PT Inka.

UPGRADES ON TRACK The refleeting program of the Philippine National Railways (PNR) gets a boost with the acquisition of three diesel hydraulic locomotives and 15 passenger coaches from Indonesian manufacturer PT Inka. It arrives at De la Rosa Station in Makati City, next to another PT Inka train (painted white), which was shipped in 2019. —RICHARD A. REYES

MANILA, Philippines — In a bid to modernize the country’s rail transport, President Ferdinand “Bongbong” Marcos Jr. has directed the Department of Transportation (DOTr) to go back to the negotiating table to secure the loan agreements for three big-ticket railway projects after China failed to act on the country’s funding request, Transportation Undersecretary Cesar Chavez said on Saturday.

Chavez, in a statement, said Marcos was referring to the Subic-Clark Railway Project, the Philippine National Railways (PNR) South Long-Haul Project and the Davao-Digos segment of the Mindanao Railway Project (MRP).

Article continues after this advertisement

The three said projects were to be funded under China’s official development assistance (ODA) through loan agreements between the governments of the Republic of the Philippines and the People’s Republic of China.

FEATURED STORIES

But the loan agreements on the said projects are now considered “withdrawn” after the Chinese government failed to act on the funding requests by the former Duterte administration, according to Chavez.

“There was a policy discussion on three China ODA rail projects in last Tuesday’s cabinet meeting which the President commented that as a matter of policy, we should encourage more investments in rail and that we should focus more on rail transport,” Chavez said.

Article continues after this advertisement

Last January, the contract for the P142 billion PNR South Long-Haul Project — also called the PNR Bicol Express — was awarded to the joint venture of China Railway Group Ltd., China Railway No. 3 Engineering Group Co. Ltd., and China Railway Engineering Consulting Group Co. Ltd.

Article continues after this advertisement

The contract for the construction of the P51-billion Subic-Clark Railway Project was awarded to China Harbour Engineering Co. in December 2020.

Article continues after this advertisement

Meanwhile, the P83-billion Tagum-Davao-Digos segment of the MRP failed to proceed after China was unable to submit a shortlist of contractors for its design-build contract.

Chavez said the Department of Finance informed China Eximbank that the submitted loan applications would only be valid until May 31, 2022, and would be automatically withdrawn if not then approved.

Article continues after this advertisement

Finance Secretary Carlos Dominguez III later decided to cancel the loan applications with China in the light of the upcoming transition of government and in deference to the incoming administration.

RELATED STORIES:

PH scraps China loan deals for Duterte rail projects

JMS
Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the and acknowledge that I have read the .

pop
sports
sports
business
entertainment
TAGS: China, DoTr

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the and acknowledge that I have read the .

© Copyright 1997-2024 | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies.