黑料社

Makati relocatees finally see the light

MANILA, Philippines鈥擲ome 700 families who were relocated from danger zones in Makati City to Calauan, Laguna province, will soon be seeing the light, literally speaking.

According to the Makati government, it has finally secured the permits necessary for the electrification of the 40-hectare Makati Homeville.

It added in a statement that on Thursday, its Department of Engineering and Public Works (DEPW) received from Calauan town officials the Fire Safety Inspection Certificate and Certificate of Final Electrical Inspection.

As a result, the Manila Electric Co. (Meralco) can start installing electric posts and other lighting equipment for the benefit of some 700 families living in the relocation site next week.

The relocatees used to live in danger zones or 鈥減ublic domains鈥 in Barangays Rizal, West Rembo, East Rembo, Poblacion, Guadalupe Viejo, Guadalupe Nuevo, Pio del Pilar, Valenzuela, Bangkal, Palanan and San Isidro.

Peter Dizon, DEPW engineer, said the 鈥渄elay鈥 in the electrification of the site stemmed from the 鈥渘egligence鈥 of the contractor, Twin Leaf Group Inc., during the first phase of the site鈥檚聽聽 development from 2008 to 2010.

According to Dizon, the contractor, without first securing the necessary building permits from the Calauan government, constructed a health center, two two-story public school buildings and a covered court.

Although the Calauan government granted Twin Leaf a site development permit in 2008, it reportedly failed to comply with the conditions set by local officials, resulting in the permit鈥檚 cancellation in 2011. The DEPW consequently submitted an alteration plan on Feb. 10, 2014.

Geronimo Comaling, head of the DEPW鈥檚 survey and land improvement section, said it took the Makati government 鈥測ears to rectify the violations and finally obtain the approval鈥 of the Calauan government.

On Saturday, the Inquirer tried calling the phone numbers of Twin Leaf that were listed online to get a reaction but to no avail.

According to Dizon, Christian Magnaye of the Meralco branch in San Pablo, Laguna, said that the installation of electric posts, cables and transformers would take 鈥渁bout two to three weeks.鈥

The first building to be hooked up to the power source would be the health center followed by the 鈥渞est of the buildings and 395 completed household units in the area,鈥 he added.

On the other hand, the Makati City government said that it was working on the requirements for the installation of potable water sources in all households on the relocation site.

At present, residents get their drinking water from pumps in the area and communal faucets with a submeter installed by Laguna Water District (LWD).

The city government said the LWD would 鈥渆ventually鈥 deliver 鈥渂ulk water through a mother meter and supply water to all households through the site鈥檚 water pipe system.鈥

LATEST STORIES
Read more...