Rain, floods cause delays in North-South Commuter Railway construction | Inquirer

Rain, floods cause delays in North-South Commuter Railway construction

By: - Reporter /
/ 03:46 PM August 07, 2023

The recent heavy rainfall and flooding caused by typhoons and the southwest monsoon have caused delays in the construction of North-South Commuter Railway (NSCR) project.

The 38-kilometer PNR Clark Phase 1 railway in Balagtas, Bulacan on Monday, June 14, 2021, the 1st segment of the massive North-South Commuter Railway. It has 10 stations, spanning the cities of Manila, Caloocan, Valenzuela Meycauayan and Malolos, and is set to open in 2024. Photo by Niño Jesus Orbeta/Philippine Daily Inquirer)

MANILA, Philippines — The recent heavy rainfall and flooding caused by typhoons and the southwest monsoon have caused delays in the construction of North-South Commuter Railway (NSCR) project.

Transportation Secretary Jaime Bautista said this on Monday after he received reports from contractors and consultants for NSCR’s northern segment.

Article continues after this advertisement

This part connects Pampanga and Metro Manila.

FEATURED STORIES

“Floods hit ongoing construction of several rail stations, which were caused by increasing volume of water in nearby rivers,” the project’s general consultants told the DOTr secretary in a meeting.

They added delays may stretch to ten days or possibly two weeks more.

Article continues after this advertisement

Due to this, Bautista ordered contractors to implement a catch-up plan.

Article continues after this advertisement

Meanwhile, clean-up operations are being carried out.

Article continues after this advertisement

NSCR is a 147-kilometer rail transport route comprising 37 stations and 464 train cars.

It stretches across 28 cities and municipalities in Central Luzon, Metro Manila, and Calabarzon.

Article continues after this advertisement

Once fully operational, it is expected to serve over a million passengers a day.

RELATED STORIES:

Bongbong Marcos sees 3,000 new jobs from South Commuter Railway Project

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the and acknowledge that I have read the .

P52.1-B deals keep Laguna-Pampanga rail project on track

APL
MOST READ
www
entertainment
www
sports
entertainment
entertainment
TAGS: Construction, delay, DoTr, NSCR, Railway

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the and acknowledge that I have read the .

© Copyright 1997-2024 | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies.