Phase 1 of LRT 1 Cavite Extension is 98.2% completed

Phase 1 of LRT 1 Cavite Extension is 98.2% completed

By: - Reporter /
/ 02:42 PM June 07, 2024

PHOTO: LRT-1 Dr. Santos Station Intermodal Facility STORY: Phase 1 of LRT 1 Cavite Extension is 98.2% completed

LRT-1 Dr. Santos Station Intermodal Facility —Photo from Light Rail Manila Corp.

MANILA, Philippines — The construction of Cavite Extension Phase 1 of the Light Rail Transit Line 1 is already 98.2 percent complete as of April, according to a statement issued by the on Friday.

The Cavite Extension Phase 1 will add 6.2 km to the existing LRT 1 line, from Baclaran Station in Pasay City to Dr. Santos Station in Parañaque City.

Article continues after this advertisement

READ: LRT Cavite extension project phase 1 to open by year-end

FEATURED STORIES

With the first phase nearing completion, all five new stations under the Parañaque extension currently have a progress rate of above 90 percent, as follows:

  • Redemptorist Station: 97.4%
  • MIA Station: 97.2%
  • Asia World Station: 90.4%
  • Ninoy Aquino Station: 93.5%
  • Dr. Santos Station: 97.7%

“The nearing completion of the LRT-1 Cavite Extension Phase 1 is a testament to the government and private sector’s commitment to improving public transportation in the country,” LRMC General Manager Enrico Benipayo said in a statement.

Article continues after this advertisement
PHOTO: LRT-1 Dr. Santos Station

LRT-1 Dr. Santos Station —Photo from Light Rail Manila Corp.

“An excellent showcase of how public-private partnership (PPP) works, this project underscores LRMC’s commitment to providing a safe, convenient, and passenger-centric commuting experience for everyone,” he added.

Article continues after this advertisement

The LRMC said all five stations will be under 24/7 CCTV monitoring and are equipped with two elevators per station, as well as escalators for both northbound and southbound passengers.

Article continues after this advertisement

Tactile paving will also be installed in each station for visually impaired passengers, along with common areas and restrooms for passengers.

All new stations will also have real-time passenger information systems showing arrival and departure times.

Article continues after this advertisement

Each station will also have designated breastfeeding rooms and commercial spaces available for lease.

After completing the first phase, LRMC will proceed with the second phase, consisting of Las Piñas Station and Zapote Station, and then the third and last phase, the Niog Station.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the and acknowledge that I have read the .

EDITORS' PICK
pop
business
entertainment
cebudailynews
business
globalnation
TAGS: Light Rail Manila Corp., LRT 1 Cavite Extension

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the and acknowledge that I have read the .

© Copyright 1997-2024 | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies.