MANILA, Philippines —  Several areas in Luzon will experience power interruptions from November 5 to 10 due to scheduled maintenance activities, said the Manila Electrical Company (Meralco).

The affected areas include parts of Metro Manila, Bulacan, Laguna, Quezon Province, Batangas, and Cavite.

Based on Meralco’s website, listed below are the areas that will be affected by the power interruptions:

Article continues after this advertisement

November 5 – 6, 2024 – Bulacan (Bulakan town and Malolos City)

FEATURED STORIES

Between 11 p.m. Nov. 5 to 4 a.m. November 6:

  • Portion of Circuit Sta. Maria 423YU, Portion of Matungao Road from Daang Estacion St. to Camino Real Road in Bgy. San Jose, Bulakan.
  • Portion of Bagumbayan St. from Sta. Ana St. to and including various subdivisions and sitios in Bulakan.
  • Portion of Arterial Road from Maysantol Road to Sitio Pulong Dulo St. in Sitio Pulong Dulo, Bgy. Look 2nd, Malolos City including Aina Homes Subd. and Masagana Homes Subd. Phases 1 & 2.
  • Portion of Bulacan, Maysantol, Camino Real, Sta. Ana Roads from Dariusville Subd. to Dulo St. including various subdivisions and sitios in Bulakan.
    • REASON: Line reconductoring and reconstruction works, relocation of facilities and replacement of poles along Camino Real Road and Bagumbayan St. in Bgys. Maysantol and Bagumbayan in Bulakan, Bulacan.

November 4 – 5, 2024 – Quezon City (Novaliches)

Article continues after this advertisement

Between 11 p.m. Nov. 4  to 4 a.m. Nov. 5

Article continues after this advertisement
  • Portion of Circuit Novaliches – 49YJ
  • Portion of Commonwealth Ave. from Iglesia Ni Cristo – Lokal Ng Fairview to Tullahan Bridge III in Neopolitan Subd. Phase 6 and North Fairview Subd. including SSS North Fairview Homes, Namasape HOA Inc. Compound and Namapa Compound in Bgys. Pasong Putik and North Fairview.
    • REASON: Line reconstruction works along Commonwealth Ave. in Bgy. Pasong Putik, Novaliches, Quezon City.

November 6 – 7, 2024 – Quezon City (Matandang Balara)

Article continues after this advertisement

Between 11:15 p.m. Nov. 6 to 5:15 a.m. Nov. 7

  • Portion of Circuit Diliman 423VU, Portion of South Zuzuarregui St. from Capitol Hills Drive to near Commonwealth Ave. including various compounds and subdivisions in Bgy. Matandang Balara.
    • REASON: Line reconductoring works along South Zuzuarregui St. in Bgy. Matandang Balara, Quezon City.

READ:

Article continues after this advertisement

November 6, 2024 – Batangas Province (Batangas City)

Between 11 a.m. and 2 p.m.

  • Portion of Circuit Batangas 325SG
  • Portion of Caltex Road from near Vinseth Trading & Construction Supply Shop to 4J’s Carwash & Detailing Services Shop including portion of Meralco Road in Bgy. Banaba South
  • Portion of Banaba South Barangay Road from Caltex Road.
    • REASON: Line reconductoring works along Caltex Road in Bgy. Banaba South, Batangas City, Batangas Province.

November 6 – 7, 2024 – Quezon City (Greater Lagro and Pasong Putik)

Between 11 p.m. Nov 6 and 4 a.m. Nov. 7

  • Portion of Circuits North Caloocan 414NOC, Novaliches 47YJ
  • Portion of Quirino Highway from Meralco – North Caloocan substation to and including various establishments in Bgys. Pasong Putik and Greater Lagro.
  • Portion of Fr. F. Palao St. from Quirino Highway to and including Mater Carmeli School in Sacred Heart Village 2 in Bgy. Pasong Putik.
    • REASON: Relocation of facilities affected by MRT-7 construction along Quirino Highway in Bgys. Pasong Putik and Greater Lagro, Quezon City.

November 7, 2024 – Taguig City (New Lower Bicutan And Hagonoy)

Between 12:15 a.m. and 4:15 a.m.

  • Portion of Circuit Gardner 55G, Portion of MRT Ave. from M. L. Quezon Ave. to C-6 Road in Bgys. New Lower Bicutan and Hagonoy; portion of C-6 Road and nearby streets in Taguig City.
    • REASON: Replacement and relocation of poles, line reconductoring works, and installation of additional lightning protection devices along MRT Ave. in Bgys. New Lower Bicutan and Hagonoy in Taguig City.

November 7 – 8, 2024 – Laguna (Nagcarlan)

Between 10 p.m. Nov. 7 and 2 a.m. Nov. 8

  • Portion of Circuit Botocan 41D
  • Portion of Silangan Road from near Balinacon – Malinao Road to and including Playboyz Talyer in Bgy. Silangan Ilaya.
    • REASON: Upgrading, installation, and retirement of facilities along Silangan Road in Bgy. Silangan Ilaya, Nagcarlan, Laguna.

November 7 – 8, 2024 – Laguna (Nagcarlan, Rizal, and San Pablo City)

Between 11:30 p.m. Nov. 7 and 12:01 a.m. Nov. 8; between 5 a.m. and 5:30 a.m. Nov. 8.

  • Portion of Circuit Botocan 41D
  • Portion of Nagcarlan – Rizal Road from near El Patio’s Event Place to and including Sitio Biuyan in Bgy. Sto. Cristo, San Pablo City; and Viriña Compound; various Bgys. in Rizal.
    • REASON: Upgrading, installation, and retirement of facilities along Silangan Road in Bgy. Silangan Ilaya, Nagcarlan, Laguna.

November 7, 2024 – Batangas Province (Batangas City)

Between 10 a.m. and 1 p.m.

  • Portion of San Jose – Ibaan – Batangas National Road from Playmates KTV Bar in Bgy. Balagtas to Sabang Bridge including various establishments and subdivisions in Bgys. Soro-Soro Ilaya, Soro-Soro Karsada, Soro-Soro Ibaba, Tinga Itaas, Tinga Labak and Balagtas.
    • REASON: Replacement of poles along San Jose – Ibaan – Batangas National Road, Bgy. Balagtas, Batangas City, Batangas Province.

November 7 – 8, 2024 – Taguig City (Bagong Tanyag)

Between 11:15 p.m. Nov. 7 and 4:15 a.m. Nov. 8

  • Portion of Tanyag St. from Mañalac Ave. to and including Purok 1 – 7; and Bagong Tanyag Integrated School.
    • REASON: Line reconductoring works and installation of facilities along Tanyag St. in Bgy. Bagong Tanyag, Taguig City.

November 7 – 8, 2024 – Laguna (Cabuyao City)

Between 11 p.m. Nov. 7 and 4 a.m. Nov. 8

  • Portion of Maharlika Highway from Putol St. in Bgy. San Isidro to and including various establishments in Bgy. Banlic.
    • REASON: Line reconstruction works along Maharlika Highway in Bgys. San Isidro and Banlic in Cabuyao City, Laguna.

November 8 – 9, 2024 – Laguna (Luisiana and Majayjay) and Quezon province (Lucban)

Between 11 p.m. Nov. 8 and 4 a.m. Nov. 9

  • Portion of Lucban-Luisiana Road and various streets in Luisiana, Laguna
  • Portion of Majayjay-Luisiana Road and Bala St. including Bgys. in Luisiana and Lucban, Quezon Province.
    • REASON: Relocation of poles, line reconductoring works, and line reconstruction works at various areas in Luisiana, Laguna.

READ: Telcos, Meralco to restore services in areas affected by storm

November 9, 2024 – Cavite (Bacoor City) and Las Piñas City (Talon II)

Between 12:15 a.m. and 5:15 a.m.

  • Portion of BF Resort and Vatican City Drives from B. Estanislao St. to Zapote River Drive, including Dear Joe – Coffee and Juice in San Nicolas III, Bacoor City, Cavite
  • Various streets in BF Resort Village and Vista Grande Village in Bgy. Talon II, Las Piñas City.
    • REASON: Installation of facilities and line reconductoring works along BF Resort Drive in BF Resort Village, Bgy. Talon II, Las Piñas City.

November 9 – 10, 2024 – Bulacan (Pulilan)

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our daily newsletter

By providing an email address. I agree to the and acknowledge that I have read the .

Between 11 p.m. and 11:45 p.m. Nov. 9 and between 6:15 a.m. and 7 a.m. Nov. 10.

  • Northstar World Steel in Bgy. Dampol I. Froneri Phils. Inc. in Bgy. Tibag.
    • REASON: Replacement of rotten poles in Bgy. Dampol 1, Pulilan, Bulacan.
TAGS: MERALCO, Power Interruption

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Subscribe to our newsletter!

By providing an email address. I agree to the and acknowledge that I have read the .

© Copyright 1997-2024 ºÚÁÏÉç | All Rights Reserved

This is an information message

We use cookies to enhance your experience. By continuing, you agree to our use of cookies.